Schedule

The STEP project was officially launched in March 2017, and is a six-year government-industry collaboration with three distinct budget periods.

Budget period 1 (ends October 2018)
Detailed Facility and Equipment Design (25 months)
  • System analysis, P&IDs, Component Specs
  • Design major equipment
  • Procure heat source, cooling tower and long-lead items
  • Materials and seal tests
  • Start site construction
Budget Period 2 (ends January 2021)
Fabrication and Construction (27 months)
  • Complete site construction and civil works
  • Fabrication and installation of major equipment
  • Commissioning and simple-cycle test
  • Start site construction
Budget Period 3 (ends September 2022)
Facility Operation and Testing (20 months)
  • Facility reconfiguration
  • Test recompression cycle

Interested in partnering?

Understand how sCO2 technology can improve high-efficiency
power generation in your industry and how you can become part of STEP Demo.

STEP-DEMO-logo_511x200

For more information, contact Markus Lesemann directly or call 818.405.9564

Scroll To Top